Kamoa-Kakula nears Phase 2 completion, Ivanhoe bids Farren farewell
TSX-listed Ivanhoe Mines reports that the 3.8-million-tonne-a-year Phase 2 concentrator plant at its 39.6%-owned Kamoa-Kakula project in the Democratic Republic of Congo is expected to be 93% complete by January 31, with hot commissioning of the concentrator on track to start in April. Ivanhoe co-chairpersons Robert Friedland and Yufeng “Miles” Sun note that this schedule is at the front end of its previous guidance of being in the second quarter, as well as several months ahead of the original schedule.